Additional
Project AKA : Benderson Development
Approval Date : 05-25-2016
Total Cost : $5,380,000.00
Approval Date : 05-25-2016
Total Cost : $5,380,000.00
Project Details
The project entails the construction of a spec building in the Town of Cheektowaga. The 100,000 sq. ft. facility will create first class, clean and productive office, warehouse and distribution space at moderate rental costs ideally suited to start up and expansion minded businesses.
The current project mirrors one previously approved by this Board in April, 2015 which consisted of two spec buildings totaling 100,000 sq. ft. in the neighboring Broadway Development Park also in the Town of Cheektowaga.
Since the 2008 recession, construction of new industrial space has been put on hold. During this time, demand has grown to the point that the existing supply is at near capacity.
Project Files
Application:
Project Log:
Public Hearing Transcript:
Agent Agreement:
1st Amendment to Agent Agreement:
Inducement Resolution:
PILOT Agreement:
Economic Impact Analysis:
Status Details
4/25/16 - Public hearing held.
5/25/2016 - ECIDA Board of Directors adopts a Negative Declaration in accordance with SEQRA.
5/25/2016 - Lease/Leaseback Inducement Resolution presented to the Board of Directors