Project Details

 

The project consists of the expansion and renovation of the existing facility. 25,000  additional square feet is being added to east and west portions of the building to allow for expanded manufacturing, warehouse and office space.

 

Additional parking areas will be added to accommodate anticipated future employment growth.  As part of this expansion of the parking area, the New York State Department of Environmental Conservation is requiring the installation of a costly underground water detention system to handle water runoff.

 

Status Details

 5/23/16- Public Hearing held.  

6/22/16- ECIDA Board of Directors adopts a Negative Declaration in accordance with SEQRA.