Great Lakes Orthodontics, LLC
Address
200 Cooper Avenue
Tonawanda
New York
14150
Additional
Approval Date : 06-22-2016
Total Cost : $5,005,230.00
Total Cost : $5,005,230.00
Project Details
The project consists of the expansion and renovation of the existing facility. 25,000 additional square feet is being added to east and west portions of the building to allow for expanded manufacturing, warehouse and office space.
Additional parking areas will be added to accommodate anticipated future employment growth. As part of this expansion of the parking area, the New York State Department of Environmental Conservation is requiring the installation of a costly underground water detention system to handle water runoff.
Project Files
Application:
Project Log:
Public Hearing Transcript:
Agent Agreement:
Inducement Resolution:
PILOT Agreement:
Economic Impact Analysis:
Status Details
5/23/16- Public Hearing held.
6/22/16- ECIDA Board of Directors adopts a Negative Declaration in accordance with SEQRA.
6/22/16- Lease/Leaseback Inducement Resolution presented to the Board of Directors.